- ClientThe Nairn Golf Club
- Date2019-2020
- RolePrincipal Designer
- TeamStephen McCann - Neil Montgomery (retired)
We worked for the client, The Nairn Golf Club, on redesigning and constructing the course layout in the ancient fishing port and market town and royal burgh of Nairn in the Highlands of Scotland.
We were engaged as the contract's Principal Designer (PD), overseeing the planning phase and the general health and safety on-site during the works.
We were appointed as the project's CDM Principal Designer (PD). Our roles included checking the Principal Contractor’s Construction Phase Plan (CPP) and reviewing the Risk Assessment and Method Statement (RAMS) and the asbestos removal Plan of Works.
Throughout the project, we carried out monthly audits, which started with the CDM compliance audit and continued with the monthly safety compliance audit.
- Produce the Pre-Construction Information
- Review and approve the Risk Assessments and Method Statement and issue a report
- Carry out the pre-start CDM audit and issue a report
- Carry out monthly site audits and issue a report on the progress
- Carry out the completion site audit and issue a report
- Ensure the completion of the Health & Safety File